by Radha Kunjabihari das | Sep 17, 2021 | Announcements
Construction of our much awaited temple is progressing at a smooth pace.Currently, the elevator work is in progress. Approval of dual gas service for existing structure throughout the winter season was obtained. Perimeter parapet wall and kicker base have...
by Radha Kunjabihari das | Sep 12, 2021 | Announcements
During last week, erection of beam between col. 4B and 4C along with perimeter angle for the roof was completed. Roof deck was also finished. Water service was brought into the mechanical room .Storm drain at northern property and roof frames were setup as...
by Radha Kunjabihari das | Jul 30, 2021 | Announcements
Construction is going on as per schedule. Steel framing work will continue for a few more...
by Radha Kunjabihari das | Jul 23, 2021 | Announcements
Construction Update: July 19 th The reinforced concrete foundation for the main building is in place. Steel framing is currently in...
by Radha Kunjabihari das | Jul 17, 2021 | Announcements
Construction Update: July 17 th Temple construction started on Rama-navami day. Steel framing work will continue for few more weeks. Everything is moving on schedule as...
by Radha Kunjabihari das | Jul 10, 2021 | Announcements
Construction Update: July 5th Due to long weekend, there was minimal activity on the construction front to report this week. In the current structure, the openings for skylight all the way up three stories is clearly visible. We can literally feel and comprehend the...