by Radha Kunjabihari das | Dec 18, 2021 | Announcements
Rough Carpentry framing is complete for third floor office rooms and mechanical room on first...
by Radha Kunjabihari das | Dec 11, 2021 | Announcements
Concrete infill at stair treads STR 1,2,3 are completed. Roofing ISO, TPO and flashing 98% is completed – remaining 2% are related to electrical and plumbing penetrations.Rough carpentry at first floor kitchen and stairwell enclosures are progressing Mechanical duct...
by Radha Kunjabihari das | Nov 13, 2021 | Announcements
First Floor concrete has been laid out and Second Floor concrete is 50% complete.Blown in insulation on roof parapet is done, roof ISO and TPO membranes are at 60% completion.Curb at Skylite is finished. Roofing work of Sri Sri Radha madam is under progress. First...
by Radha Kunjabihari das | Oct 16, 2021 | Announcements
RTU penetrations and zone dampers are 60% complete. Exterior sheathing is...
by Radha Kunjabihari das | Oct 9, 2021 | Announcements
The dream of Naperville community to build a grand temple for Sri Sri Radha Syamasundara is slowly but steadily being realized. In this phase of construction, work is progressing at a steady pace. Framing of stairs #3 and roof access have been completed. Deck and...
by Radha Kunjabihari das | Sep 25, 2021 | Announcements
Perimeter parapet roof studding is 85% complete. Perimeter exterior wall framing is 70% done. Underground plumbing penetrations have been finished along with steel framing for all the stairs which is 95%...